Punch list
A punch list (also known as a snagging list) is a document that is prepared close to the end of a construction project and issued by the appropriate certifying authority (typically, the architect, contract administrator or employer’s agent). It lists any faults that are identified or works that do not conform to the specifications, which should be rectified prior to a certificate of practical completion being issued.
Generally, snagging refers to a process that takes place a fortnight or so prior to practical completion when an area is considered complete by a contractor and is offered ready for inspection. It is a slang expression widely used in the construction industry to define the process of inspection necessary to compile a list of minor defects or omissions (snages) in building works for the contractor to rectify.
For more information, see Snagging.
This differs from a work-to-complete list which is compiled by a contractor and issued to each subcontractor and their crews at, or near, completion - a list of the remaining items and any defective work that subcontractors are required to complete before leaving the site.
For more information, see Work-to-complete list.
The process of inspection and going through a punch list is usually performed close to the end, if not right at the end, of construction so that the work as a whole can be reviewed and checked. The list of items to be completed or corrected is compiled by the contractor and submitted to the employer’s agent or designer (usually the architect or engineer). Lists tend to be organised either by room or by trade.
Following this, the work is inspected by the agent (sometimes along with the contractor, subcontractor, owner, and any other relevant stakeholders) to determine whether the items on the list have been resolved. Traditionally, the list would be worked through and a hole punched in the margin to indicate that the particular item of work had been completed, hence the term ‘punch list’. Today, digital software is capable of producing virtual punch lists with applications that can be operated via mobile devices as well as more complex web and desktop varieties.
Typical examples of punch list items include: repairing broken windows, replacing missing roof tiles, repainting chipped paintwork, filling cracks, and so on.
Once the list of items has been completed according to the specifications in the contract, or a mutually agreed resolution has been decided upon for certain items, practical completion can be certified.
Following practical completion, there is generally a defects liability period, during which the contractor may be recalled to rectify defects which appear. This is not a chance to correct snagging items apparent at practical completion, If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued.
For more information see: Practical completion.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.